The company carried out the jacking and installation of the 130-metre-long steel structure in Bertem, on behalf of Victor Buyck Steel Construction.
The operation involved four CS1000 jacking towers and 126 axle lines of K24-ST SPMTs to move the bridge 230 metres from its assembly area to its final position.
The new infrastructure will improve road safety by eliminating intermediate supports in the motorway median, while its construction alongside the E40 helped limit disruption to traffic.
Sarens, world leader in heavy lifting, engineered transport and crane rental services, has jacked and installed the new bowstring bridge over the E40 motorway in Bertem, Belgium, on behalf of its client Victor Buyck Steel Construction. Weighing approximately 4000 tons following the addition of its concrete deck and measuring 130 metres long, 27 metres wide and 30 metres high, the new steel bridge replaces the former Tervuursesteenweg (N3) crossing, which had deteriorated and could no longer be renovated.
Sarens was responsible for the jacking and installation of the structure, carrying out the works in two separate phases between July and October 2026. During the first phase, from July 14th to 24th, the Sarens team used four CS1000 jacking towers to raise the bridge, which weighed approximately 1,800 tons at this stage, to the required transport height. In the second phase, between September 30th and October 16th, following the addition of the concrete deck, the structure was transported from its assembly area alongside the motorway to its final installation position, approximately 230 metres away.
For this operation, Sarens deployed 126 axle lines of K24-ST SPMTs (Self-Propelled Modular Transporters), supported by six Power Pack Units (PPUs). The installation had to be completed within a limited timeframe during a full overnight closure of the E40 motorway, requiring meticulous engineering and planning to ensure the safe and precise movement of the structure.
One of the main challenges involved the inclination of the road in two directions, which required a detailed analysis of the trailer path using AutoCAD. Furthermore, to prevent torsion in the bridge deck during transport, an inclinometer monitoring system was installed at both ends of the structure, connected to a central readout. This enabled the SPMT operator to continuously monitor the level of the transporters and make the necessary adjustments throughout the journey.
The logistics phase also required careful coordination. The equipment was transported mainly by truck from Sarens' headquarters, involving approximately 35 truck movements each way. The set-up of the equipment on site took around one week, with a peak workforce of eight Sarens professionals involved in the operation.
According to Kenny Decoster, Project Manager at Sarens, “This project required detailed planning and close coordination between our engineering and operational teams. The inclination of the transport route and the need to maintain the stability of such a large structure during the movement were key challenges. By combining our CS1000 jacking system with the K24-ST SPMTs and a continuous monitoring system, we were able to manage the operation with the precision required and complete the installation within the scheduled motorway closure window.”
The new bowstring bridge is part of the wider renewal of the Tervuursesteenweg crossing, commissioned by the Flemish Roads and Traffic Agency (Agentschap Wegen en Verkeer). Its 130-metre span allows the E40 to be crossed without intermediate supports in the motorway median, an important safety consideration given the high traffic volumes and the proximity of the E40-E314 interchange. The project also includes improvements to the surrounding road infrastructure, with the renewal of the Tervuursesteenweg and the provision of wider, segregated cycle paths. By assembling the structure alongside the motorway before moving it into position during a planned overnight closure, the construction method also helped limit disruption to road users throughout the works.
Over the past few years, Sarens has established itself as a strategic player in the installation and renovation of bridges around the world. Its recent projects include the installation of the 2,600-tonne Pyramid Bridge over the Ringvaart Canal in Ghent (Belgium), the replacement of the historic 140-year-old Ponte al Pino bridge over a key high-speed railway line in Florence (Italy), and the installation of a 278-tonne wooden pedestrian and cycle bridge at the Vier Armen junction in Tervuren (Belgium). Sarens has also been involved in major road and railway infrastructure projects, including the installation of the 5,850-tonne OA14 bridge in Bettembourg (Luxembourg).
About Sarens
Sarens is the global leader and reference in crane rental, heavy lift and engineered transportation services. With state-of-the-art equipment, value engineering, one of the world's largest inventories of cranes, transporters and special rigging equipment, Sarens offers creative and intelligent solutions to today's heavy lifting and engineering transport challenges.
With more than 100 entities in 70 countries operating without borders, Sarens is an ideal partner for small to large-scale projects. Sarens currently employs 6,500 highly qualified professionals who are ready to serve the needs of any client worldwide and in all market sectors. https://www.sarens.com/